AIR LIQUIDE PROJECT AT YENAKIIEVE IRON AND STEEL PLANT

Yenakievo, Donetsk region


Start of construction: 27 February 2013 
Сompletion of construction: 31 May 2014


Types of work: GENERAL CONTRACTOR, CONSTRUCTION WORKS

 

The construction of an air separation plant with a production capacity of 1700 tons of oxygen, nitrogen and argon gas per day.

This project was completed in partnership with French company Air Liquide – a leader of industrial gas manufacturing. This investment project is one of the biggest of its kind in CIS countries.

Total area: 22 435 m2